(A) failure of a critical component identified in the preliminary design report;(B) failure of a programable logic controller;
(C) membrane unit shutdown;
(D) clearwell water level above the maximum or below the minimum;
(E) chlorine residual level above the maximum or below the minimum;
(F) low level in a chemical storage tank;
(G) loss of electrical power;
(H) unauthorized entry; and
(I) low interior temperature of a treatment building.
(9) Facility Startup.
(a) A membrane filtration facility shall be equipped to allow for disposal of feedwater and filtrate during the startup process.
(b) Prior to installing membrane modules:
(i) piping shall be flushed to remove dirt and construction debris;
(ii) chemical-feed equipment shall be tested to assure:
(A) proper operation; and
(B) delivery of chemicals at proper dosages;
(iii) mechanical equipment shall be tested for leaks and proper operation;
(iv) instrumentation shall be calibrated and tested for proper operation;
(v) the control system shall be verified for:
(A) digital and analog control inputs and outputs;
(B) instrumentation alarm limits;
(C) programming logic;
(D) instrumentation loops; and
(E) operational sequences.
(c) After installation, a membrane module shall be:
(i) flushed to waste to remove the storage solution; and
(ii) tested to assure smooth startup and shutdown.
(d) A water supplier shall comply with applicable disposal requirements for waste flushed from newly installed piping, tanks, equipment, and membranes at a membrane filtration facility.
(e) Prior to use of a membrane filtration facility to provide drinking water:
(i) pipes, tanks, and associated equipment shall be disinfected and flushed according to AWWA procedures;
(ii) membrane modules shall be disinfected and flushed according to instructions from the membrane manufacturer taking into consideration the chlorine tolerance of the membranes;
(iii) a facility shall be operated continuously for a trial period to verify design parameters;
(iv) treated water quality shall be sampled and demonstrate compliance with drinking water standards;
(v) final, operational control limits for direct integrity testing shall be established;
(vi) a DIT shall be done per Subsection R309-215-15(18)(b)(iii), and the result may not exceed the established upper control limit; and
(vii) a water supplier shall obtain an operating permit as required by Section R309-500-9.
(f) A water supplier shall assure that adequate operator training and instruction are provided by the supplier of the membrane units on each aspect of startup and operation of a membrane filtration facility.
(10) Operating Permit -- Additional Information. In addition to meeting the requirements for an operating permit in Section R309-500-9, a water supplier requesting an operating permit for a membrane filtration facility treating surface water or groundwater under the direct influence of surface water shall provide to the division:
(a) a statement acknowledging that the facility startup requirements of Subsection R309-530-8(9) have been completed;
(b) normalized operating flux range;
(c) normalized operating flux per membrane unit;
(d) maximum operating differential pressure for a membrane unit;
(e) membrane unit backwashing frequency;
(f) membrane unit clean-in-place frequency;
(g) minimum, verified, operational, direct integrity testing resolution;
(h) maximum, verified, operational, direct integrity testing sensitivity;
(i) verified, operational, direct integrity testing control limit; and
(j) verified, indirect integrity monitoring performance-based upper control limit.
(11) Operational Membrane Integrity Testing and Monitoring and Reporting.
(a) Membrane Integrity Testing and Monitoring.
(i) Direct Integrity Testing.
(A) A water system using membrane filtration to treat surface water or groundwater under the direct influence of surface water to meet the requirements of Section R309-530-8 shall comply with the direct integrity testing requirements of Subsection R309-215-15(18)(b)(iii).
(B) A DIT shall be done on a membrane unit following: