(i) Conduct a failure analysis on all assets.(ii) Determine probability of failure.
(iii) Analyze risk and consequences of failure.
(iv) Prioritize system assets based on importance to system operation.
(v) Develop specific response plans based on potential asset failure.
(d) Minimum infrastructure life-cycle costs.
(i) Implement an appropriate maintenance schedule, including costs for all assets.
(ii) Identify life-cycle costs for all assets.
(iii) Develop a capital improvement plan and an operations and maintenance strategy.
(iv) Identify and compare the cost of rehabilitation versus replacement.
(v) Determine the related costs of responding to asset failure.
(e) Long-term budgeting strategy.
(i) Regularly review system budget.
(ii) Establish and fund a capital facilities account.
(iii) Implement a rate structure to ensure financial sustainability.
(iv) Explore asset renewal and replacement financing.
(v) Identify financial assistance resources based on asset condition and importance.
(4) All water systems subject to this rule shall complete the following:
(a) Prepare and asset management plan as described in Subsection R309-800-5(3).
(b) System's governing body shall formally adopt the asset management plan.
(c) Submit proof of adoption to the Division.
(5) In addition to the requirements in Subsection R309-800-5(4), water systems applying for financial assistance from either the federal or state Drinking Water State Revolving Fund Financial Assistance Program must also submit their asset management plan to the Division for review or request sufficient funds to create an asset management plan. Asset management plans prepared using financial assistance from the Drinking Water Board shall be submitted to the Division for review.
R309-800-6. Requirements for New Community and New Non-transient, Non-community Water Systems.
(1) Each proposed, new water system must demonstrate that it has adequate technical, managerial, and financial capacity before it may provide water for human consumption. These water systems shall submit the following for Capacity Assessment Review.
(a) Project Notification form, available on the Division's website.
(b) A business plan, which includes a facilities plan, management plan, financial plan, and an asset management plan.
(i) Facilities plan. The facilities plan shall describe the scope of the water services to be provided and shall include the following.
(A) A description of the nature and extent of the area to be served and provisions for extending the water supply system to include additional area. The description shall include population and land use projections and forecasts of water usage.
(B) An assessment of current and expected drinking water compliance based on monitoring data from the proposed water source.
(C) A description of the alternatives considered, including interconnections with other existing water systems, and the reasons for selecting the method of providing water service. This description shall include the technical, managerial, financial, and operational reasons for the selected method.
(D) An engineering description of the facilities to be constructed, including construction and future phases, and plans for expansion. This description shall include an estimate of the full cost of any required construction, operation, and maintenance.
(ii) Management plan. The management plan shall describe what is needed to provide for effective management and operation of the system, and shall include the following:
(A) Documentation that the water system has the legal right and authority to take the measures necessary for the construction, operation, and maintenance of the system. The documentation shall include evidence of ownership.
(B) An operating plan that describes the tasks to be performed in managing and operating the system. The operating plan shall consist of administrative and management organization charts, plans for staffing the system with certified operators, and provisions for an operations and maintenance manual.
(C) Documentation of credentials of management and operations personnel, cooperative agreements, or service contracts including demonstration of compliance with Rule R309-300 water system operator certification rule.
(iii) Financial plan. The financial plan shall describe the water system's expected revenues, cash flow, and issuance and repayment of debt for meeting the costs of construction, and the estimated costs of operation and maintenance for at least five years from the date the water system expects to begin operation.
(iv) Asset Management Plan. The asset management plan shall include all the elements described in Subsection R309-800-5(3).
(c) After the information required in this section has been submitted by the water system and is deemed complete, the Division shall conduct a Capacity Assessment Review. The water system shall be notified in writing whether or not the new system has demonstrated adequate capacity. No new community or non-transient, non-community system will be approved if it lacks adequate capacity.