R315-124-6. Procedures for Decisionmaking -- Draft Permits.(a) Once an application is complete, the director shall tentatively decide whether to prepare a draft permit or to deny the application.
(b) If the director tentatively decides to deny the permit application, the director shall issue a notice of intent to deny. A notice of intent to deny the permit application is a type of draft permit that follows the procedures for a draft permit prepared under Section R315-124-6. If the director's final decision is that the tentative decision to deny the permit application was incorrect, the director shall withdraw the notice of intent to deny and prepare a draft permit under Subsection R315-124-6(d).
(c) Reserved.
(d) If the director decides to prepare a draft permit, the director shall prepare a draft permit that contains the following information:
(1) each condition under Sections R315-270-30 and R315-270-32 for hazardous waste facilities;
(2) each compliance schedule under Section R315-270-33 for hazardous waste facilities;
(3) the monitoring requirements under Section R315-270-31 for hazardous waste facilities;
(4) the information required for permits issued under Rules R315-15, R315-17, and R315-301 through R315-320; and
(5) standards for treatment, storage, and disposal, or any combination of the three, and other permit conditions under Section R315-270-30 for hazardous waste facilities.
(e) Each draft permit prepared by the director under Section R315-124-6 shall be accompanied by a statement of basis or fact sheet, and shall be based on the administrative record, publicly noticed and made available for public comment. The director shall give notice of opportunity for a public hearing, issue a final decision, and respond to comments.
R315-124-7. Procedures for Decisionmaking -- Statement of Basis.
The director shall prepare a statement of basis for every draft permit that a fact sheet under Section R315-124-8 is not prepared. The statement of basis shall briefly describe the conditions of the draft permit and the reasons for them or, in the case of notices of intent to deny or terminate, reasons supporting the tentative decision. The statement of basis shall be sent to the applicant and, on request, to any other person.
R315-124-8. Procedures for Decisionmaking -- Fact Sheet.
(a) A fact sheet shall be prepared for every draft permit if a statement of basis is not prepared. The fact sheet shall briefly set forth the principal facts and the significant factual, legal, methodological and policy questions considered in preparing the draft permit. The director shall send this fact sheet to the applicant and, on request, to any other person.
(b) The fact sheet shall include, when applicable:
(1) a brief description of the type of facility or activity that is the subject of the draft permit;
(2) the type and quantity of wastes, fluids, or pollutants that are proposed to be or are being treated, stored, disposed of, injected, emitted, or discharged;
(3) Reserved;
(4) a brief summary of the basis for the draft permit conditions, including references to applicable statutory or regulatory provisions and appropriate supporting references to the administrative record required by Section R315-124-9;
(5) reasons why any requested variances or alternatives to required standards were granted or denied;
(6) a description of the procedures for reaching a final decision on the draft permit including:
(i) the beginning and ending dates of the comment period under Section R315-124-10 and the address where comments will be received;
(ii) procedures for requesting a hearing and the nature of that hearing; and
(iii) any other procedures that the public may participate in the final decision;
(7) name and telephone number of a person to contact for additional information.
R315-124-9. Procedures for Decisionmaking -- Administrative Record for Draft Permits.
(a) The provisions of a draft permit prepared by the director under Section R315-124-6 shall be based on the administrative record defined in Section R305-7-209 and Section R315-124-18.
(b) Section R315-124-9 applies to draft permits when public notice was given after the effective date of Rule R315-124.
R315-124-10. Procedures for Decisionmaking -- Public Notice of Permit Actions and Public Comment Period.
(a) Scope.
(1) The director shall give public notice that the following actions have occurred:
(i) a permit application has been tentatively denied under Subsection R315-124-6(b); or
(ii) a draft permit has been prepared under Subsection R315-124-6(d); or
(iii) a hearing has been scheduled under Section R315-124-12;
(2) Unless the director decides to submit the request to public notice, comment, or hearing under Subsection R315-124-5(b), no public notice is required if a request for permit modification, revocation and reissuance, or termination is denied under Subsection R315-124-5(b). Written notice of that denial shall be given to the requester and to the permittee.
(3) Public notices may describe more than one permit or permit actions.
(b) Timing.