NOTICE OF SUBSTANTIVE CHANGE
TYPE OF FILING: Amendment
1. Agency Information
Natural Resources; Oil, Gas and Mining; Oil and Gas
Department of Natural Resources
1594 W North Temple, Suite 1210
2. Contact Persons
Please address questions regarding information on this notice to the persons listed above.
3. General Information
A. Rule or section catchline:
R649-3-26. Seismic Exploration
B. Purpose of the new rule or reason for the change:
The Division of Oil, Gas and Mining (Division) is updating their bond requirements for Oil and Gas wells, including bond amounts for seismic exploration.
C. Summary of the new rule or change:
This rule filing added a performance bond amount of $10,000 for any seismic exploration conducted in the state.
5. Fiscal Information
Provide an estimate and written explanation of the aggregate anticipated cost or savings to:
There is a total of one state agency, the Division of Oil, Gas and Mining, that will be associated with this proposed rule change. There will be a fiscal impact of $10,000 per seismic exploration, however, the Division cannot estimate how many operators will conduct seismic exploration activities.
No local government fiscal impact is anticipated since this rule only impacts oil and gas operators, the Division, and the Board.
C. Small businesses ("small business" means a business employing 1-49 persons):
There are 303 small business oil and gas operators (for a complete listing of NAICS codes used in this analysis, please contact the agency) in the state of Utah.
There will be a fiscal impact of $10,000 per seismic exploration, however, the Division cannot estimate how many operators will conduct seismic exploration activities.
D. Non-small businesses ("non-small business" means a business employing 50 or more persons):
There are a total of 4 non-small business oil and gas operators (for a complete listing of NAICS codes used in this analysis, please contact the agency) in the state of Utah.
There will be a fiscal impact of $10,000 per seismic exploration, however, the Division cannot estimate how many operators will conduct seismic exploration activities.
E. Persons other than small businesses, non-small businesses, state, or local government entities ("person" means any individual, partnership, corporation, association, governmental entity, or public or private organization of any character other than an agency):
This rule change will not affect persons other than small businesses, businesses, or local governments as this rule only applies to small and non-small business operators and the Division.
F. Compliance costs for affected persons:
There will be a compliance cost of $10,000, however, the Division cannot estimate how many operators will conduct seismic exploration activities.
6. Regulatory Impact Summary Table
Enter the cost or savings in the relevant cell. If there is no cost or savings, enter, "$0." If a cost or savings is inestimable, enter, "inestimable."
7. Regulatory Impact Analysis Approval
The Commissioner of the Department of Natural Resources, Joel Ferry, has reviewed and approved this regulatory impact analysis.
8. Family Impact Information
A. The agency has considered this rule's impact on family health, stability, and formation:
9. Citation Information
Provide citations to the statutory authority for the rule. If there is also a federal requirement for the rule, provide a citation to that requirement:
11. Public Notice Information
The public may submit written or oral comments to the agency identified in box 1.
A. Comments will be accepted until:
12. Effective Date Information
This rule change MAY become effective on:
(NOTE: This is the date the agency anticipates making the filing effective. It is NOT the effective date)
13. Agency Authorization Information
Agency head or
designee and title:
R649. Natural Resources; Oil, Gas and Mining; Oil and Gas.
R649-3. Drilling and Operating Practices.
R649-3-26. Seismic Exploration.
(1)[.] Form 1, Application for Permit to Conduct Seismic Exploration shall be submitted to the division by the seismic contractor at least seven days before[prior to] commencing any type of seismic exploration operations. In cases of emergency, approval may be obtained either verbally or by telegraphic communication. (a)[1.1.] Changes of plans or line locations may be implemented in an emergency situation without division approval. (b)[1.2.] Within five days after the change is performed, the seismic contractor shall submit written notice of the change to the division. (c)[1.3.] The permit may be revoked at any time by the division for failure to comply with the rules and orders of the board. (d)[1.4.] Any request to deviate from the general plugging and operations procedures of Title R649[these rules] shall be included on the permit application. (e)[1.5.] The name, address, and telephone number of the seismic contractor's local contact shall be submitted to the division as soon as determined if not available when the permit application is submitted. (j)[5.10.] The coarse bentonite plugging material shall have the following specifications - chemically unaltered sodium bentonite, coarse ground, three quarter inch maximum size, not more than 19% moisture content and not more than 15% inert solids by volume.(6)[.] Form 2, Seismic Exploration Completion Report shall be submitted to the [D]division within 60 days after completion of each seismic exploration project. The report shall include: Certification by the seismic contractor that any shot holes have been plugged as prescribed by the division. KEY: oil and gas law
Date of Last Change: 2026[December 3, 2025] Notice of Continuation: June 30, 2025
Authorizing, and Implemented or Interpreted Law: 40-6-1 et seq.; 40-6-5; 40-6-20; 40-6-21
!--dar--