(B) An imminent threat to the public health, safety, welfare or environment exists which warrants injunctive or other emergency relief; or(C) A pattern of continuous, significant violations exists such that administrative enforcement action alone is unlikely to achieve compliance; or
(D) The court is the most convenient or appropriate forum for resolution of the dispute.
(ii) Criminal: referral to the County Prosecutor or the Attorney General's Office for prosecution or criminal investigation where:
(A) The alleged act or failure to act may be defined as a criminal offense by state law;
(B) Enforcement is beyond the jurisdiction or investigative capability of the State Engineer; or
(C) Criminal sanctions may be appropriate.
(d) Miscellaneous - other enforcement options may be pursued to achieve compliance. Additional options include, but are not limited to:
(i) Joint actions with, or referrals to, other federal, state or local agencies;
(ii) Direct legal or equitable actions in state or federal court; and/or
(iii) Denial, suspension or revocation of state-granted licenses, approvals permits or certifications.
(2) Unless otherwise stated, all notices, orders and judgments are effective upon the date issued.
(3) Combinations of enforcement actions are not mutually exclusive and may be concurrent and/or cumulative.
(4) An IO may be incorporated into a Default Order if the respondent fails to participate as defined herein.
R655-14-12. Administrative Penalties and Administrative Costs.
(1) Pursuant to Sections 73-2-1 and 73-2-25 and these rules, the Enforcement Engineer shall assess the initial administrative penalties, which may include an administrative fine, a requirement to replace water and the reimbursement of enforcement costs to which the respondent may be subject for any violation as set forth in Subsection 73-2-25(2)(a).
(2) No penalty shall exceed the maximum penalty allowed by Subsection 73-2-26(1), as may be amended.
(3) Each day a violation is repeated, continued or remains in place, constitutes a separate violation.
(4) The penalty imposed shall begin on the first day the violation occurred, and may continue to accrue through and including the day the Notice of Violation and/or Cease and Desist Order is issued, or the Final Judgment and Order is issued, or until compliance is achieved.
(5) The amount of the penalty shall be calculated based on:
(a) The value or quantity of water unlawfully taken, including the cost or difficulty of replacing the water;
(b) The gravity of the violation, including the economic injury or impact to others;
(c) Whether the respondent attempted to comply with the State Engineer's orders; and
(d) The respondent's economic benefit from the violation.
(6) Enforcement costs, interest, late payment charges, costs of compliance inspections, and collection costs may be assessed in addition to the administrative fine. These include:
(a) Enforcement costs: Costs for time spent by Division staff, supervisors, the Presiding Officer, and personnel of the Attorney General's Office, at the full cost of each employee's hourly rate, including salary, benefits, overhead and other directly related costs.
(b) Late payment charges: Costs accrued at the monthly percentage rate assessed by the Utah Department of Administrative Services, Office of Debt Collections.
(c) Compliance inspection costs: Time spent by Division staff at the full cost of each employee's hourly rate, including salary, benefits, overhead and other directly related costs.
(d) Collection costs: Actual collection costs.
(7) The State Engineer may report the total amount of administrative fines and/or enforcement costs assessed to consumer reporting agencies and pursue collection as provided by Utah law.
(8) Any monies collected under Section 73-2-26 and these rules shall be deposited into the General Fund.
R655-14-13. Replacement of Water.
(1) In addition to administrative fines and enforcement costs, the Enforcement Engineer may impose and the Presiding Officer may order the respondent to replace up to 200 percent of water unlawfully taken in accordance with Section 73-2-26.
(2) The Presiding Officer may order actual replacement of water after:
(a) A respondent fails to request judicial review of a Final Judgment and Order issued under Section 73-2-25; or
(b) Completion of judicial review, including any appeals.
(3) Pursuant to Section 73-2-26, and before imposing or ordering replacement of water, the Enforcement Engineer and the Presiding Officer shall consider the following factors:
(a) The value or quantity of water unlawfully taken, including the cost or difficulty of replacing the water;
(b) The gravity of the violation, including the economic injury or impact to others;
(c) Whether the respondent attempted to comply with the State Engineer's orders; and
(d) The respondent's economic benefit from the violation.
(4) The Enforcement Engineer may require and the Presiding Officer may order the respondent to submit a plan to replace water, which shall be submitted in writing and contain the following information:
(a) The name and mailing address of the respondent or persons submitting the plan;
(b) The State Engineer Agency Action (SEAA) number assigned to the IO;