(iv) To calculate the total uncompleted work amount, the department shall use the amount shown on the contractor's "Status of Work Under Contract" form found in the department's bid system.(v) The process described in this Subsection (5) does not apply to contractors prequalified as "unlimited."
(c) If the department determines it is necessary to issue an addendum to the plans and specifications during the advertising period, the department shall post the addenda in the department's bid system.
(6)(a) Each bidder shall submit a sealed bid to the department within the department bid system before the time and at the place specified in the notice to contractors.
(b) The department shall open bids publicly at the time and place indicated in the notice to contractors.
(c) The department may only consider a bid if the bid is accompanied by a bid security in the form and amount stated in the notice to contractors.
(d)(i) Except as provided in Subsection (6)(d)(ii), a bidder must be licensed as required by Title 58, Occupations and Professions, to engage in the work described in the notice to contractors before submitting a bid.
(ii) A contractor may submit a bid on a Federal-aid highway project without having first obtained a license if the contractor obtains a valid Utah license before starting any work under the contract.
(e) The department may reject any or all bids.
(7)(a) If the department awards a contract to a bidder, the department shall award the contract:
(i) to the lowest responsive, responsible, and qualified bidder; and
(ii) within 30 calendar days after the opening of bids or within a timeframe agreed upon by the department and the successful bidder.
(b) When all bids received exceed the engineer's estimate by more than 10%, the department may accept a bid as described in Subsection (6)(a) or reject all bids.
(c) The department shall notify a successful bidder by email, using the email address shown on the bidder's bid.
R916-1-9. Design-Build Contracts.
(1) This section applies only when the department uses a solicitation for a design-build construction project.
(2) The department may;
(a) issue an RFQ soliciting qualification statements from potential proposers wishing to submit proposals for a design-build project;
(b) forgo issuing an RFQ and invite potential proposers that are prequalified in accordance with Rule R916-2 to submit proposals for a design-build project pursuant to an RFP.
(3) When the department issues an RFP for a design-build construction project, the department may:
(a) ask for initial proposals followed by clarifications, communications, or discussions, and may request best and final offers; or
(b) award the contract without clarifications, communications, discussions, or requesting best and final offers.
(4) When the department issues an RFP for a design-build construction project, the department may ask for proposals based on a predetermined sum.
(5)(a) The department may award a stipend to a proposer who submits a responsive proposal but who is not awarded a contract for the project.
(b) If the department elects to award a stipend as described in Subsection (5)(a), the department shall identify the amount of the stipend in the RFP.
(6)(a) The department shall include in the RFP separate technical and price proposals.
(b) The department shall treat technical solutions or design concepts contained in proposals as proprietary information unless the proposer receives a stipend as described in Subsection (5)(a) and as provided in the RFP.
(c) In accordance with Subsection 63G-2-305(6), the department may not disclose a proposal or other information submitted to the department in response to an RFP until after the contract is awarded and signed by all parties.
(7) When procuring a design-build project, the department may follow any of the criteria described in 23 CFR 636.
(8)(a) The department shall state the basis for an award in the solicitation.
(b) To meet the requirement of Section 63G-6a-1402 of only awarding a contract to the responsible proposer whose proposal is most advantageous to the department or the state, the department may only base an award of an RFP on the following approaches:
(i) Award to the responsible proposer offering the lowest-priced responsive proposal. If the solicitation includes a mandatory technical level, the department may not consider a proposal responsive unless it meets that mandatory level.
(ii) Award to the responsible proposer whose proposal is evaluated as providing the best value to the department.
(iii) If the solicitation provides for a specified sum, award to the responsible proposer whose proposal is evaluated as providing the best value to the department.
(c) If the department awards the contract, the department shall execute the contract and issue a notice to proceed when the department is ready for the contractor to proceed with the work.
R916-1-10. Construction Manager/General Contractor and PDB Contracts.
(1)(a) To procure a CMGC or PDB project, the department shall issue a solicitation with an accompanying RFP or RFQ.
(b) For the RFP or RFQ described in Subsection (1)(a), the department: