(i) Limit visible dust opacity from vehicular operations.(ii) Stabilize staging area soils during use.
(iii) Stabilize staging area soils at project completion.
(o) Stockpiling.
(i) Stabilize stockpile materials during and after handling.
(ii) Stabilize surface soils where support equipment and vehicles will operate.
(p) Trackout prevention and cleanup.
(i) Install and maintain trackout control devices in effective condition at all access points where paved and unpaved access or travel routes intersect.
(q) Traffic on unpaved routes and parking areas.
(i) Stabilize surface soils where support equipment and vehicles will operate.
(r) Trenching.
(i) Stabilize surface soils where trenching equipment, support equipment and vehicles will operate.
(ii) Stabilize soils after trenching.
(s) Truck loading.
(i) Empty loader bucket slowly and keep loader bucket close to the truck to minimize the drop height while dumping.
(ii) Stabilize surface soils where support equipment and vehicles will operate.
(5) The fugitive dust control plan must include contact information, site address, total area of disturbance, expected start and completion dates, identification of dust suppressant and plan certification by signature of a responsible person.
R307-309-7. Storage, Hauling and Handling of Aggregate Materials.
Any person owning, operating or maintaining a new or existing material storage, handling or hauling operation shall prevent, to the maximum extent possible, and in accordance with R307-309-6, material from being deposited onto any paved road other than a designated deposit site. Any such person who deposits materials that may create fugitive dust on a public or private paved road shall clean the road promptly.
R307-309-8. Construction and Demolition Activities.
Any person engaging in clearing or leveling of land with an area of one-quarter acre or more, earthmoving, excavating, construction, demolition, or moving trucks or construction equipment over cleared land or access haul roads shall prevent, to the maximum extent possible, and in accordance with R307-309-6, material from being deposited onto any paved road other than a designated deposit site. Any such person who deposits materials that may create fugitive dust on a public or private paved road shall clean the road promptly.
R307-309-9. Roads.
(1) Any person responsible for construction or maintenance of any existing road or having right-of-way easement or possessing the right to use the same whose activities result in fugitive dust from the road shall minimize fugitive dust to the maximum extent possible and in accordance with R307-309-6. Any such person who deposits materials that may create fugitive dust on a public or private paved road shall clean the road promptly.
(2) Unpaved Roads. Any person responsible for construction or maintenance of any new or existing unpaved road shall prevent, to the maximum extent possible, the deposit of material from the unpaved road onto any intersecting paved road during construction or maintenance. Any person who deposits materials that may create fugitive dust on a public or private paved road shall clean the road promptly.
R307-309-10. Mining Activities.
(1) In addition to the requirements under R307-309-1 through R307-309-6, fugitive dust, construction activities, and roadways associated with mining activities are regulated under the provisions of R307-309-10.
(2) Any person who owns or operates a mining operation shall minimize fugitive dust as an integral part of site preparation, mining activities, and reclamation operations.
(3) The fugitive dust control measures to be used shall include:
(a) Periodic watering of unpaved roads or;
(b) Use of chemical stabilizers on unpaved roads or;
(c) Paving of roads.
(d) Immediate removal of coal, rock minerals, soil, and other dust-forming debris from roads and frequent scraping and compaction of unpaved roads to stabilize the road surface.
(e) Restricting the speed of vehicles in and around the mining operation,
(f) Revegetating, mulching, or otherwise stabilizing the surface of all areas adjoining roads that are a source of fugitive dust.
(g) Restricting the travel of vehicles on other than established roads.
(h) Enclosing, covering, watering, or otherwise treating loaded haul trucks and railroad cars, to minimize loss of material to wind and spillage.
(i) Substitution of conveyor systems for haul trucks and covering of conveyor systems when conveyed loads are subject to wind erosion.