(i) Rule R307-403, Permits: New and Modified Sources in Nonattainment Areas and Maintenance Areas;(ii) Rule R307-405, Permits: Major Sources in Attainment or Unclassified Areas (PSD);
(iii) Rule R307-406, Visibility;
(iv) Rule R307-410, Permits: Emissions Impact Analysis;
(v) Rule R307-420, Permits: Ozone Offset Requirements in Davis and Salt Lake Counties; or
(vi) Rule R307-421, Permits: PM10 Offset Requirements in Salt Lake County and Utah County.
(k) Any other information necessary to determine if the proposed construction, modification, installation, or establishment will be in accord with Title R307.
(l) The payment of a new source review fee established under Subsection 19-1-201(6)(i).
(3) Notwithstanding the exemptions in Sections R307-401-9 through R307-401-16, any person that is subject to Rule R307-403, R307-405, or R307-406 shall submit a notice of intent to the director and receive an approval order precedent to the construction, modification, installation, establishment, or relocation of an air pollutant source or indirect source.
R307-401-6. Review Period.
(1) Completeness Determination. Within 30 days after receipt of a notice of intent, or any additional information necessary to the review, the director will advise the applicant of any deficiency in the notice of intent or the information submitted.
(2) Within 90 days after the receipt of a complete application including the information described in Section R307-401-5, the director will:
(a) issue an approval order for the proposed construction, installation, modification, relocation, or establishment pursuant to the requirements of Section R307-401-8; or
(b) issue an order prohibiting the proposed construction, installation, modification, relocation or establishment if it is determined that any part of the proposal will not be in accord with the requirements of Title R307.
(3) The review period under Subsection R307-401-6(2) may be extended by up to three 30-day extensions if more time is needed to review the proposal.
R307-401-7. Public Notice.
(1) Issuing the Notice. Before issuing an approval or disapproval order of the proposed construction, installation, modification, relocation, or establishment, the director shall:
(a) publish a legal notice of the intent to approve or disapprove on the public legal notice website under Subsection 45-1-101(2);
(b) notify the public of the intent to approve or disapprove on the Division's website; and
(c) post the draft permit and administrative record for the draft permit, or information on how to access the administrative record for the draft permit, on the Division's website during the public comment period.
(2) Opportunity for Review and Comment.
(a) At least one location will be provided where the information submitted by the owner or operator, the director's analysis of the notice of intent proposal, and the proposed approval order conditions will be available for public inspection.
(b) Public Comment.
(i) A 30-day public comment period will be established.
(ii) A request to extend the length of the comment period, up to 30 days, may be submitted to the director within 15 days of the date the legal notice in Subsection R307-401-7(1)(a) is published.
(iii) Public Hearing. A request for a hearing on the proposed approval or disapproval order may be submitted to the director within 15 days of the date the legal notice in Subsection R307-401-7(1)(a) is published.
(iv) The hearing will be held in the area of the proposed construction, installation, modification, relocation, or establishment.
(v) The public comment and hearing procedure may not be required when an order is issued to extend the time required by the director to review plans and specifications.
(3) The director will consider comments received during the public comment period and at the public hearing and, if appropriate, will make changes to the proposal in response to comments before issuing an approval order or disapproval order.
R307-401-8. Approval Order.
(1) The director will issue an approval order if the following conditions have been met:
(a) The degree of pollution control for emissions, to include fugitive emissions and fugitive dust, is at least best available control technology. When determining best available control technology for a new or modified source in an ozone nonattainment or maintenance area that will emit volatile organic compounds or nitrogen oxides, best available control technology shall be at least as stringent as any Control Technique Guidance document that has been published by EPA that applies to the source.
(b) The proposed installation will meet the applicable requirements of:
(i) Rule R307-403, Permits: New and Modified Sources in Nonattainment Areas and Maintenance Areas;
(ii) Rule R307-405, Permits: Major Sources in Attainment or Unclassified Areas (PSD);
(iii) Rule R307-406, Visibility;
(iv) Rule R307-410, Permits: Emissions Impact Analysis;