(c) Be written in the same language as the text of the contract or agreement for the renovation or, in the case of non-owner occupied target housing, in the same language as the lease or rental agreement or the pamphlet.R307-841-5. Work Practice Standards.
(1) Standards for renovation activities. Renovations must be performed by firms certified under Section R307-841-7 using renovators certified under Section R307-841-8. The responsibilities of certified firms are set forth in Subsection R307-841-7(4) and the responsibilities of certified renovators are set forth in Subsection R307-841-8(2). (a) Occupant protection. Firms must post signs clearly defining the work area and warning occupants and other persons not involved in renovation activities to remain outside of the work area. To the extent practicable, these signs must be in the primary language of the occupants. These signs must be posted before beginning the renovation, must remain in place, and must be readable until the renovation and the post-renovation cleaning verification have been completed. If warning signs have been posted in accordance with 24 CFR 35.1345(b)(2) or 29 CFR 1926.62(m), additional signs are not required by this section.
(b) Containing the work area. Before beginning the renovation, the firm must isolate the work area so that no dust or debris leaves the work area while the renovation is being performed. In addition, the firm must maintain the integrity of the containment by ensuring that any plastic or other impermeable materials are not torn or displaced, and taking any other steps necessary to ensure that no dust or debris leaves the work area while the renovation is being performed. The firm must also ensure that containment is installed in such a manner that it does not interfere with occupant and worker egress in an emergency.
(i) Interior renovations. The firm must:
(A) Remove all objects from the work area, including furniture, rugs, and window coverings, or cover them with plastic sheeting or other impermeable material with all seams and edges taped or otherwise sealed;
(B) Close and cover all duct openings in the work area with taped-down plastic sheeting or other impermeable material;
(C) Close windows and doors in the work area. Doors must be covered with plastic sheeting or other impermeable material. Doors used as an entrance to the work area must be covered with plastic sheeting or other impermeable material in a manner that allows workers to pass through while confining dust and debris to the work area;
(D) Cover the floor surface, including installed carpet, with taped-down plastic sheeting or other impermeable material in the work area six[6] feet beyond the perimeter of surfaces undergoing renovation or a sufficient distance to contain the dust, whichever is greater. Floor containment measures may stop at the edge of the vertical barrier when using a vertical containment system consisting of impermeable barriers that extend from the floor to the ceiling and are tightly sealed at joints with the floor, ceiling, and walls; and (E) Use precautions to ensure that all personnel, tools, and other items, including the exterior of containers of waste, are free of dust and debris before leaving the work area.
(ii) Exterior renovations. The firm must:
(A) Close all doors and windows within 20 feet of the renovation. On multi-story buildings, close all doors and windows within 20 feet of the renovation on the same floor as the renovation, and close all doors and windows on all floors below that are the same horizontal distance from the renovation;
(B) Ensure that doors within the work area that will be used while the job is being performed are covered with plastic sheeting or other impermeable material in a manner that allows workers to pass through while confining dust and debris to the work area;
(C) Cover the ground with plastic sheeting or other disposable impermeable material extending [10]ten feet beyond the perimeter of surfaces undergoing renovation or a sufficient distance to collect falling paint debris, whichever is greater, unless the property line prevents [10]ten feet of such ground covering. Ground containment measures may stop at the edge of the vertical barrier when using a vertical containment system; and (D) If the renovation will affect surfaces within [10]ten feet of the property line, the renovation firm must erect vertical containment or equivalent extra precautions in containing the work area to ensure that dust and debris from the renovation does not contaminate adjacent buildings or migrate to adjacent properties. Vertical containment or equivalent extra precautions in containing the work area may also be necessary in other situations [in order ]to prevent contamination of other buildings, other areas of the property, or adjacent buildings or properties. (c) Prohibited and restricted practices. The work practices listed [below ]are prohibited or restricted during a renovation as follows: (i) Open-flame burning or torching of painted surfaces is prohibited;
(ii) The use of machines designed to remove paint or other surface coatings through high speed operation such as sanding, grinding, power planning, needle gun, abrasive blasting, or sandblasting, is prohibited on painted surfaces unless such machines have shrouds or containment systems and are equipped with a HEPA vacuum attachment to collect dust and debris at the point of generation. Machines must be operated so that no visible dust or release of air occurs outside the shroud or containment system; and
(iii) Operating a heat gun on painted surfaces is permitted only at temperatures below 1,100 degrees Fahrenheit.
(d) Waste from renovations.
(i) Waste from renovation activities must be contained to prevent releases of dust and debris before the waste is removed from the work area for storage or disposal. If a chute is used to remove waste from the work area, it must be covered.
(ii) At the conclusion of each work day and at the conclusion of the renovation, waste that has been collected from renovation activities must be stored under containment, in an enclosure, or behind a barrier that prevents release of dust and debris out of the work area and prevents access to dust and debris.
(iii) [When]If the firm transports waste from renovation activities, the firm must contain the waste to prevent release of dust and debris. (e) Cleaning the work area. After the renovation has been completed, the firm must clean the work area until no dust, debris, or residue remains.
(i) Interior and exterior renovations. The firm must:
(A) Collect all paint chips and debris and, without dispersing any of it, seal this material in a heavy-duty bag; and
(B) Remove the protective sheeting. Mist the sheeting before folding it, fold the dirty side inward, and either tape shut to seal or seal in heavy-duty bags. Sheeting used to isolate contaminated rooms from non-contaminated rooms must remain in place until after the cleaning and removal of other sheeting. Dispose of the sheeting as waste.
(ii) Additional cleaning for interior renovations. The firm must clean all objects and surfaces in the work area and within [2]two feet of the work area in the following manner, cleaning from higher to lower: (A) Walls. Clean walls starting at the ceiling and working down to the floor by either vacuuming with a HEPA vacuum or wiping with a damp cloth;