(d) install fire-tube and water-tube power boilers and hot water heating boilers, including fittings and piping, valves, gauges, pumps, radiators, converters, fuel oil tanks, fuel lines, chimney flues, heat insulation and other devices, apparatus, and equipment related thereto, in a system not connected to the culinary water system, or connected to the culinary water system but separated from the culinary water system by a backflow prevention device;(e) install water conditioning equipment and only such pipe and fittings as are necessary for connecting the water conditioning equipment to the water supply system within the premises;
(f) install sewer, sewer lines, sewage disposal, septic tank, drainage, and the construction of sewage disposal plants and appurtenances thereto.
(2) Inclusions and Exclusions. The scope described in Subsection 301y(1) includes:
(a) Incidental excavation, cabling, horizontal boring, grading, trenching, backfilling, concrete work, or asphalt work necessary for construction of any work related to this scope of practice; and
(b) installation of a backflow preventer device, if during each renewal period the licensee completes at least two of their six required Section R156-55a-303b continuing education hours in continuing education directly related to backflow installation.
(c) Work related to natural gas if the individual performing such work has received natural gas technician certification under Section R156-55a-308b.
(3) Subcontracting and Hiring. An S370 licensee providing services under this Chapter may not subcontract or hire any person to perform work on a project outside the scope defined in Subsection R156-55a-301y(1) except holders of an S410 -- Boiler, Pipeline, Waste Water, and Water Conditioner Contractor may hire or subcontract a Certified Natural Gas Technician for work with natural gas that requires an RMGA certificate holder under Section R156-55a-308b.
R156-55a-301z. Specialty Contractors -- S220 Carpentry and Flooring Contractor.
The scope of practice for an S220-- Carpentry and Flooring Contractor as a specialty contractor license under Subsection 58-55-301(2)(x) is defined in this subsection.
(1) Scope. A licensee under this subsection may construct, fabricate, install, place, tie, weld, or repair using:
(a) wood, wood products, metal, aluminum, metal products, metal studs, vinyl materials, plastic, rubber, fiberglass, polyethylene, thermoplastic polymers, countertops, cabinets, millwork, garage doors, doors, trim, tub liners, wall systems, partitions, or other wood, plastic, rubber, or metal composite or any composite that is by custom and usage accepted in the building industry as carpentry for structural, non-structural, and finish purposes;
(b) metal or steel structures and sheet metal, including metal cornices, marquees, metal soffits, flashings, skylights, and skydomes;
(c) metal structural studs and bearing walls, reinforcing bars, erecting shapes, plates of any profile, perimeter cross-section that are used in structures, including riveting, welding, and rigging;
(d) laminate, tile, cement, wood, synthetic wood, or similar flooring product, including prefinished and unfinished material, sanding, staining and finishing of new and existing flooring, the underlayment, and subfloors; and
(e) mechanical insulation of pipes, ducts, or conduits.
(2) Inclusions and Exclusions. The scope described in Subsection 301z(1) includes incidental concrete work and footings, grading, and surface preparation related to this scope of work.
(3) Subcontracting and Hiring. An S220 licensee providing services under this Chapter may not subcontract or hire any person to perform work on a project outside the scope defined in Subsection R156-55a-301z(1).
R156-55a-301aa. Specialty Contractors -- S270 Drywall, Paint, and Plastering Contractor.
The scope of practice for an S270 -- Drywall, Paint, and Plastering Contractor as a specialty contractor license under Subsection 58-55-301(2)(x) is defined in this subsection.
(1) Scope. A licensee under this subsection may construct, install, fabricate, and apply drywall, gypsum, wallboard panels and assemblies, lightweight metal and non-bearing wall partitions, ceiling tile and panels, and the grid system required for placement, including:
(a) insulating media in buildings and structures for temperature control, sound control, fireproofing, mechanical insulation of pipes, ducts, or conduits;
(b) stucco, stucco to lathe, plaster, and other surfaces; and
(c) paint, varnish, shellac, stain, wax and other coatings or pigments.
(2) Inclusions and Exclusions. An S270 licensee shall ensure all work performed under this subsection is within the scope listed in Subsection R156-55a-301aa(1).
(3) Subcontracting and Hiring. An S270 licensee providing services under this Chapter may not subcontract or hire any person to perform work on a project outside the scope defined in Subsection R156-55a-301aa(1).
R156-55a-301ab. Specialty Contractors -- R200 Factory Built Housing Contractor.
The scope of practice for an R200 -- Factory Built Housing Contractor as a specialty contractor license under Subsection 58-55-301(2)(x) is defined in this subsection.
(1) Scope. A licensee under this subsection may disconnect, setup, install, or remove manufactured housing on a temporary or permanent basis.
(2) Inclusions and Exclusions. The scope described in Subsection 301ab(1)